Greenhopper 5.9.x scrum rapid board questions

grant luna April 30, 2012

I just upgraded to Greenhopper 5.9.3 and l am testing out the new scrum rapid board and the features released in the new version. I am trying to determine how to migrate away from using "versions" to group issues into sprints and begin using the new "sprint" field. The scrum rapid board "plan" mode is great and I can drop issues into the sprint. However, I can't figure out how I can easily update all of the issues in the sprint to a fix version?

Example - I have 50 issues in sprint 1. The sprint is over and we have implemented the 50 issues to production version 2.1. How can I update the 50 issues to have a fix version = 2.1 (without having to manually edit each issue).

1 answer

1 accepted

Suggest an answer

Log in or Sign up to answer
0 votes
Answer accepted
Nicholas Muldoon
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 30, 2012

Hi Grant,

Head to Reports, then the Sprint Retrospective Report. Select your recently completed Sprint and then click the View in Issue Navigator link at the top right. Finally perform a Bulk Update from under the Tools menu.

We're well aware of how time consuming this is. We will improve this in a future release, no ETA available at present.

Thanks Grant,

Nicholas Muldoon

@GreenHopperTeam

grant luna April 30, 2012

That works for me!! Thanks for the quick response. BTW - Greenhopper is an awesome product!!!