Add the field Original Estimate in my Kanban List View to the Issue-Cards

Deleted user August 20, 2013

Hi,

I want to add the field Original Estimate in my Kanban List View to the Issue-Cards. I tried

to modify the Card Style using the Plugin Configuration of Greenhopper (Project Templates).

It says, the changes apply on classic boards only. But I couldnt find out which boards I actually use, the classic or none classic ones?

I also tried to configure the board itself. No success.

Thanks for any help

Kind regards

7 answers

1 accepted

1 vote
Answer accepted
Deleted user May 4, 2014

We use the kanban and scrum boards, not the classic board. In Scrum boards the original estimate is shown, in kanban boards it is neither visible nor configurable. Currently this is not a big issue for us, so i would like to close this question from my side or hand it over to anbody else who has a bigger need for this.

Rudy Dullier January 26, 2021

For anyone finding this issue, please see this issue :

https://jira.atlassian.com/browse/JRASERVER-66973

Make Time Tracking fields available for configuration in issue detail view in Kanban boards

2 votes
Anna Henke March 19, 2018

I filed a suggestion in Atlassian's Jira:

https://jira.atlassian.com/browse/JRASERVER-66973

Please vote.

Stephan Schaumburg-Lippe June 3, 2019

Thx, I voted.

2 votes
Carolyn Nelson March 17, 2016

Add the "Time Tracking" field to your screens and then Original Estimate will be available on your issues when using Kanban.

Frederico Carneiro March 2, 2018

Hi !

 

Hi Carolyn!

I wasnt able to find this configuration.

I´ve already set "Time Tracking" field to be showed in all screen(Create, Edit, View, Bug) but no success yet.

Here is what I´m looking for:

jira_3.png

Andrew Barrett May 8, 2018

^ Im looking for the same

2 votes
Daren Edmiston December 18, 2014

if this is Kanban, why would you want to estimate them?  This should be based on the most important thing to work on.

 

Sorry the Agile Purist in me had to chime in.

David Greenfield December 18, 2014

Because customers often ask what the impact would be of moving one card before another--will it cost one day? Three? Ten?

Like # people like this
SebastienD March 31, 2015

Whatever agile approach you choose, having at least a rough idea of the effort required to perform any given task is relevant; Kanban is no exception.

Like # people like this
Greg van Berkel April 19, 2015

For us we use a kanban board for the planning stage of a ticket which then feeds into a scrum board and we'd like it to be possible to add estimations on the kanban portion of the workflow.

Netexpo B.V. October 29, 2015

Same here.

Khalid Gamal January 11, 2017

I agree with the Idea of Kanban works from the highest important to low. But this feature is needed here to show the Project manager the time each resource consume on tasks. and of course that can be used later on sprint retrospective

 

 

Like # people like this
0 votes
jesus2099 December 2, 2014

Hello,

It seems to be unfortunately still impossible in kanban, you can vote this pending ticket https://jira.atlassian.com/browse/GHS-6175 asking for those fields in kanban among other things.

0 votes
Kashyap April 13, 2014

+1 . Any update?

0 votes
AhmadDanial
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 26, 2014

He there, mb.

From the description that you have provided, it sounds like you are using the Kanban (https://confluence.atlassian.com/display/AGILE/Kanban+Board). Can you confirm on that? (This refers to the Rapid Board Kanban)

Else, you might be using the Classic Boards (https://confluence.atlassian.com/display/AGILE/Using+Classic+Task+Board+Modes).

On the other hand, can we check wehther you happen to make use of the Agile Cards plugin in your JIRA instance?

david greenfield March 23, 2014

I am running a Kanban board and do not even get the option to add original_estimate to my issue detail view. This seems overly restrictive. It's configured for the default view - how to make it appear on issue detail view?

Jeff Berndt May 12, 2015

I'd like to know that, myself!

Suggest an answer

Log in or Sign up to answer