Hi, Lucas.
You can see that your 'Done' status, for some reason is yellow. That means that its type is 'In Progress' (though it's name is done) and it will be interpreted as though by JIRA.
To fix that:
This should fix the problem and all 'Done' issues will be interpreted as done.
I hope it was helpful.
Kind regards,
Jaime Kirch da Silveira
Atlassian Cloud Support
That was it, probably someone changed the category.
Thank you very much!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No problem, Lucas. I'm glad that helped.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Had exactly the same problem. The worklow was automatically generated by jira and no one else has permissions to edit the category. So this seems to be a bug.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check your Agile board - is your "done" status mapped into the "done" column?