On Backlog, workload per person shows 'Original Time', while expected to show 'Time remaining'

BenP
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 24, 2015

My Scrum board's Estimation Statistic is defined as Original Estimate + Time Remaining.

Total Workload per assignee is expressed in Original Estimate only.

 

Consider issues that do not get completed in 1 sprint. They are typically reopened & reconsidered for the next a future sprint.  

Such issues typically need their time remaining counted towards "workload", rather than the Original Time Est.

e.g. issue is created with orignal est = 3days; issue is worked on for 1day during sprint A & moved to sprint B later. During sprint planning for sprint B, the Workload by assignee still shows with 3d estimates, while only 2 days of work is actually left.

 

Can i define the board to use time remaining for this? 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Mark_McGuire October 23, 2015

We expected the same thing.  https://jira.atlassian.com/browse/GHS-11177