My Scrum board's Estimation Statistic is defined as Original Estimate + Time Remaining.
Total Workload per assignee is expressed in Original Estimate only.
Consider issues that do not get completed in 1 sprint. They are typically reopened & reconsidered for the next a future sprint.
Such issues typically need their time remaining counted towards "workload", rather than the Original Time Est.
e.g. issue is created with orignal est = 3days; issue is worked on for 1day during sprint A & moved to sprint B later. During sprint planning for sprint B, the Workload by assignee still shows with 3d estimates, while only 2 days of work is actually left.
Can i define the board to use time remaining for this?