Chart board showing time remaining when all issues have 0 hours

Wally Lawless October 4, 2011

We are currently running JIRA 4.4 with GreenHopper 5.7.1

The issue is that on the task board, all the tasks in a version show a time remaining of 0h. I can verify the same when I go to the Issue Navigator and do an export of all the issues on the specific version. However, on the planning and chart boards, the time remaining for the version is showing 4h.

This is a pretty significant issue for us as it's causing mistrust in the data we are getting from JIRA.

Is there a solution to this?

2 answers

1 accepted

1 vote
Answer accepted
Michael Jones October 13, 2011

Wally,

I've found 'the answer' after looking through several things on the GreenHopper Confluence site. In particular in this topic at the bottom: http://confluence.atlassian.com/display/GH/Sprint+Hour+Burndown+Charts

It appears that if you don't start all your work on the day the 'sprint' is scheduled to start, then you get the effect you and I are seeing. It's a known 'issue' but not certain it's being addressed at the moment from what I can tell.

When I changed the Sprint start date to the same date I had work planned to start, the chart 'fixed' itseld and calibrated correctly.

YMMV.

0 votes
Michael Jones October 12, 2011

Am seeing the same thing here. After I moved all our Sprints to Greenhopper Versions under a single Release Version, my Hourly Burndown Charts fixed themselves, but then this morning the baseline went to 0 and the 'Estimated Hours' for the sprint also show 0, even though work is estimated and planned.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events