Hi,

I'm trying to change the max number of hours worked in Tempo Time Sheets.

My hours for the Time Tracking section in JIRA are set to 16.  (see https://confluence.atlassian.com/display/JIRA/Configuring+Time+Tracking)

My hours in Tempo are set to "unlimited"

However, whenever we enter time over 8 hours in Tempo, it gives an error that the time is over the max limit of 8 hours.  Is this a bug?  Or am I missing something?

 

Best Regards,

 

Mike

 

2 answers

1 vote
Tempo Support
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 19, 2015

Hi Mike (and Clarissa)

There was a bug fixed and released in Timesheets 7.11.2 affecting this use case. Tempo Timesheets 7.11.2 is scheduled to be upgraded on JIRA Cloud instance on Monday March 23rd. This should not be an issue after that date.

Please follow our Cloud release page for updates on upgrades.

Best regards,

Heiða Dóra

Tempo Team

0 votes
cgauterio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 17, 2015

Hi Mike,

I just tried replicating this, but I was able to log work successfully. My "Max hours per day per user" is also set to Unlimited. Can you maybe post a screenshot of the error message you receive so we can take a look?