Our development teams work on stories from multiple product backlogs. I want to put stories on a sprint and keep the story IDs from the original products. Is this possible?
Hi Carrie,
To complete Nic's answer - that will be done changing the Board filter query:
https://confluence.atlassian.com/display/AGILE/Configuring+a+Board
https://confluence.atlassian.com/display/AGILE/Configuring+Filters
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes. All you need to do is create a board which includes all the projects (or even parts of projects) that you want to work with. The boards all run off an initial "filter to tell me what issues to look at"
The most obvious one is a project filter: "Project = XYZ". But you can easily change that to "Project in (XYX, ABC, HKL) , or go further and say "Project in (ABC, XYZ) and issue-type in (bug, story, feature)"