Update sub-task status to match parent's

Anis Ahmed Chohan March 3, 2015

Hi All,

On some instances I want to move an issue from one status to another, with it's child/sub-tasks issues following it in status.

Is this possible? 

Kind Regards,

Anis Ahmed Chohan

1 answer

0 votes
Bob Swift OSS (Bob Swift Atlassian Apps)
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 3, 2015

You can add an Update issues post function (part of Update on Transition for JIRA) to the transition. In the post function you define a JQL query to determine all the other issues that need to be transitioned - see How to use JQL to find issues to update. For information on how to use update issues to do a transition, see Transition issues.