Is there a way to add estimated/planned hours at the project (not the issue) level in Tempo without doing it for every day for every person.  Say Project X is going to take an estimated 480 Hours.  Can I put that at the project level in Tempo?

1 answer

0 votes
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 2, 2015

Hi James,

The time estimation is a JIRA feature and can only be done on Issue level. In Tempo Timesheets, you can plan time on Projects, Issues and Activities (Versions and Components) but these plans are always made for a User.

In Tempo Planner you can plan time on Team level. This plan will reflect on every user in the Team. Please take a look at https://tempoplugin.jira.com/wiki/display/PLANNER022/Planner+Timeline for more information.

Kind regards,

Susanne