Any way to add a closed story to a finished sprint?

Doug Varn
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 15, 2013

I accidentally finished our sprint before adding and then immediately closing a few stories that came up unplanned mid-sprint. I'd prefer count the points for those stories back to the sprint that's now ended, but it doesn't seem possible.

1 answer

1 accepted

1 vote
Answer accepted
Ivan Tse
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 15, 2013

Once you have close issues, they won't appear in your backlog. Even if you were to bring those issues back into a state where they'll show in the backlog, the process to associate tickets to a closed sprint isn't pretty. You would need to do the following.

  1. Make the Sprint field show on your issue view
  2. Identify the sprint ID of the sprint you want to add to (https://confluence.atlassian.com/display/GHKB/Greenhopper%3A+How+to+search+for+a+Sprint+using+JQL)
  3. Edit the issue and add the sprint id to the Sprint field

At this point the Sprint custom field doesn't show the name of the sprint but the ID that is used in the database. Leaving the Sprint field exposed on your view details isn't a good idea as other users can unknowingly insert bad data. I'm not quite sure of how adding items to a close sprint will change the statistics for that sprint either.

Karie Kelly
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 15, 2013

Once a sprint is closed, even if you add it as he described, none of the sprint reports will be updated.

And, they have no way of reopening, adding, and reclosing - you'll have to locate the improvement request to vote on it.

But, we've had to do with Ivan has said. Sometimes you miss items in the backlog that end up getting resolved with something in the sprint or accidentally closing a sprint. So, we have the sprint field as editable. We determine the ID by navigating to an issue that is in the sprint, editing the field to see the actual ID, and then adding the ID to the issue you want to add and accept the fact that the sprint reports don't align.

elinordavoodi April 30, 2016

thank you Ivan