Is there a way to display a dependency chain relationship by leveraging Dependency issue type in Jira Align ?
Context:
- Lab A has 3 Feature Teams (a,b,c) that are set to deliver an Epic
- They break down the Epic into more granular pieces (Features) and as part of this they identify they cannot deliver this Epic e2e independently and they'll require support from Lab B -team b.
- At this stage they'd raise a dependency ("Lab A - team a" being the "requesting" lab) and Lab B - team b being the donor
- Lab B - team b decides to "commit" to this dependency issue type and post a typical "understand" and plan phase they decide it's Feature in size and complexity
Question
- How do I link back the Feature delivered by Lab B - team b to the original dependency requested by "Lab A - team a" so that it shoes that relationship where it originated from ?
- If then Lab B - team b identifies that in order to deliver that Feature for Lab A - team A they also need some security guardrails (made-up example) from Lab C - team C so they'd have another dependency chain, how can that be raised in Jira Align and visualised ?
Many thanks in advance for your guidance